For many years, successive governments have focused on power generation, neglecting transmission and its infrastructure.
Disregard for the upgrade and
completion of power transmission infrastructure is one of the major
problems that have plagued the nation’s power sector, investigations revealed that between 2012 and now, the Federal
Government through the Transmission Company of Nigeria has completed no
fewer that 21 power transmission projects.
Sixteen of the projects were completed in 2012, while the remaining five were inaugurated this year.
Findings showed
that of the projects completed last year, the government spent about 11
years to deliver five transmission infrastructure.
Two out of the five projects, the
2×30/40MVA, 132/33kV substation in Umuahia and the 132kV double circuit
line in Alaoji-Umuahia, both in Abia State, were commenced in November
2001, but dragged till May 2012 before they were completed.
The Mbalano-Okigwe 132kV single circuit
line in Abia State was started in September 2001, but was completed in
November 2012; while the 150MVA, 330/132/33kV transformer and the 330kV
bays in Onitsha, Anambra State, and Benin, Edo State, were completed
last year though work began on them in May 2001.
A document on transmission projects
completed in 2012, obtained exclusively by our correspondent, showed
that it took six years for the government to complete the 2x150MVA,
330/132/33kV substations and line bay at Alaoji, Cross River State.
It took four years to complete the
2x30MVA substation at Makeri in Jos, Plateau State; while the
rehabilitation of the Sokoto-Talata Mafara 132kV line was done in five
years.
The document stated that the government
spent three years on the Afam-Port Harcourt 132kV double circuit turning
in and out at the Port Harcourt main transmission station.
It disclosed that three years was also
spent on the 1x30MVA, 132/33 KV substation at Kwanar Dangora, Kano
State, while the fastest of the projects was the “reconductoring” of the
Afam-Port Harcourt 132kV line, which was completed in one year.
Four other transmission projects were
completed last year, but their commencement dates of operation were not
stated by the document.
Within the last four weeks, TCN
completed the in-house installation and inauguration of 60MVA, 45MVA and
30MVA, 132/33kV power transformers in Ibadan, Oyo State; Suleja, Niger
State; and Akure, Ondo State, respectively.
Also, a 150MVA, 330/132/33kV power
transformer provided by the World Bank through the Power Holding Company
of Nigeria’s Project Monitoring Unit was installed in collaboration
with TCN engineers within the same period in Ibadan.
Only last week, the transmission company announced the inauguration of a 80MVA substation in Tamburawa, Kano State.
However, the dates of commencement of operation of the projects completed this year were not stated in the document.
Meanwhile, top government sources at the
Ministry of Power and the TCN said the neglect for power transmission
infrastructure by successive governments led to the weak state of the
nation’s transmission network.
According to them, the quantum of power
being generated in the country is far higher than what the transmission
capacity can handle.
The officials explained that previous
administrations had focused on power generation, but relegated
transmission to the background.
A senior official in the Power ministry,
who pleaded not to be named because he was not authorised to speak on
the subject, told our correspondent in Abuja, “This warranted the poor
supply of generated power for TCN lacked the capacity to fully transmit
the quantum of electricity generated.
“The good news, however, is that the
Federal Executive Council, at its meeting last week, approved an amount
running into billions of naira for TCN in order to address this
shortfall. In addition to that, the government will get additional money
warehoused from the African Development Bank to tackle critical
problems of transmission.”
Current nationwide power generation is
around 4,000 Megawatts, but the Federal Government has announced plans
to bring up the figure to 10,000MW before the end of the year.
The state of nation’s transmission infrastructure has, however, been criticised as being too poor to handle the generated power.
This, according to sources, prompted FEC to approve the sum for the transmission company.
The Minister of Power, Prof. Chinedu
Nebo, had stated that the massive increase in generation underpinned the
need for a robust transmission grid, adding that it was the weakest
link in the power equation as it had a wheeling capacity of about
4,000MW.
Nebo said, “With government’s objective
to achieve 10,000MW by 2014 and 20,000MW in 2016, the urgent need to
expand our transmission capability to evacuate the projected additions
becomes imminent.
“A total capital outlay of $3.4bn is
required up to 2016 to bring our transmission grid to evacuate all the
generated power. Government is working out the funding of TCN’s long
term expansion plan from a mix, which will include the Transmission
Development Fund, International Development Banks and multinational
agencies.”
The minister explained that the
available installed generation capacity had risen to 6,000MW, while
generation capability had increased to 5,228MW with peak generation
slightly above 4,500MW.
“We expect to add additional generation
capacity of about 2,200MW from NIPP projects; IPPs, 292MW; and Federal
Government of Nigeria legacy assets, 514MW before the end of 2013,” the
minister added.
It was also learnt that the Federal
Government was investing in large, medium and small hydro plants with
total capacity of over 4,234MW in order to boost power generation.
No comments:
Post a Comment